CALCULATION EXAMPLE

How does the quote
reach $41.93?

This worked example uses the English calculator's default two-part PLA order. Replace every sample value with your own measured conditions before quoting a real job.

1. Sample inputs

Order quantity2Material per part120g
Filament1kg / $20Extra material5%
Print time per part8 hoursAverage power120W
Electricity$0.18/kWhMachine rate$0.50/hour
Failure rate10%Consumables$0.50/part
Hands-on labor20 min/partLabor rate$20/hour
Order overhead$1Marketplace fee6%
Cost markup30%Tax allowance0%

2. Direct cost for two parts

Adjusted material

120g × 1.05 per part

252g total
Filament

$0.02/g × 126g × 2

$5.04
Electricity

8h × 0.12kW × $0.18 × 2

$0.35
Machine time

8h × $0.50 × 2

$8.00
Hands-on labor

20/60h × $20 × 2

$13.33
Consumables + overhead

$0.50 × 2 + $1 order cost

$2.00
Direct cost$28.72

3. Add expected reprint cost

Repeatable cost per part is $2.52 material + $0.1728 electricity + $4.00 machine time + $0.50 consumables, or $7.1928. At a 90% success probability, the expected repeatable cost is $7.1928 ÷ 0.9 = $7.992.

Failure reserve($7.992 − $7.1928) × 2 = $1.5984

Direct cost plus the failure reserve gives an expected cost of $30.32.

4. Add profit and gross up for the selling fee

Expected cost$30.32
30% cost markup+ $9.10
6% fee gross-up$41.9282
Round up to cents$41.93

The two-part quote is $41.93, or $20.965 per part before any separate shipping or design charge. The per-part number changes with quantity because order overhead is shared.

5. Compare the failure-rate assumption

Failure rateExpected costFinal quote
0%$28.72$39.72
10%$30.32$41.93
20%$32.32$44.70

This comparison is not a reason to accept a high failure rate. Improve the root cause first, then use the remaining observed risk in the quote.

Not included

Shipping, CAD changes, special finishing, purchased hardware, liability and market positioning are outside this example. Verify fees and tax rules for your location.

Calculate your jobRead the full method